Auburn Bay: September Construction Update Part 2

Construction is looking great at our Canoe site! We’re so excited at how fast things are changing, we couldn’t help but share another update. Here’s a quick review of what’s been happening over the past few weeks:

East Wing:

  • Plumbing is down to deficiencies.
  • Electrical is down to third, second and first floors on the last stack of that side.

East Wing (Exterior) :

  • Shingles are completed as well as deck coverings (aside from the north side wall).
  • Siders are pulling around the outside into the courtyard as well as paper and siding.

West Wing:

  • Currently framing the third floor.
  • Plumbers have started to drill out for rough ins on the first floor.

Keep your eye on this blog for extra photos coming soon! If you want to live in this amazing Avi Urban development, give us a call at 403-536-7282 to schedule an appointment. Or visit us at aviurban.com/canoe

Tara @Canoe