The Block: Construction Update March 2014

Walking on site today there was a lot of action, with all trades on deck! Taking a tour through these new Calgary condos and townhomes, not only was there action in the individual units but also throughout the whole building.

The parkade was starting to be painted and main entance was being prepped to be poured with the finishing concrete. Here is the latest update floor by floor for The Block:

On the first floor, homes are finished being painted and custom door colors are complete. Tile to the bathroom floor, shower stall and backsplash are installed. It’s really coming together with the trim and hardwood installation to follow.

On the second floor, flooring is installed and the wide plank engineered harwood looks awesome. Appliances, toilets and all lighting are also in place. These units are pretty much complete with just final touch ups to happen.

On the third floor, drywall and taping has been completed in these units. Next step happening is texturing the ceiling, with installation of the trim and baseboards to follow.

On the fourth floor, rough-ins have started and are moving along. With all in-floor heating now installed, most units have been plumbed with electrical just about half complete.

Townhomes– North townhomes are now insulated and drywalled, with taping and texturing the ceiling to follow. The west townhomes are insulated with drywall happening next on to these homes. West townhomes also now have the exterior balconies completed with railing.

With constant work being done and things moving along, be sure to follow our Facebook page to get weekly photos and updates.