The Block: Construction Update – May 2014

It’s raining, it’s pouring, but no one was snoring on site when I walked through Friday! Even in the rain the landscapers were busy pouring gravel and prepping the planters through out the building. There was definitely an excitement being on site seeing these new Calgary condo and townhomes get closer and closer to being completed. Here is the latest update on The Block:

First and second floors are in the process of touch ups and Avi Finals. The Avi Final is a third party service we use to walk through each home to ensure it’s deficiency free and allows us to deliver a great home to you, once you do your own walk-through!

Third floor is in the finishing touches stage, with shower doors being installed this week. These homes are looking so awesome, and the finishing stage is where each apartment gets its own “personality” with your personalized selections being installed.

Fourth floor the electrical inspections are complete and are now being insulated, with drywall soon to follow. The ceilings on these homes are incredible, and drywall will really help to show how major the spaces ares!

All townhomes are drywalled and taped. North townhomes are being painted and the west townhome ceilings are being textured with painting to follow.

Parkade is complete with stall numbers painted and storage lockers installed. Interior walkway railings will be completely installed next week, check out the photos to see the railings that have already been installed. Don’t they look amazing?

We are in the final stages which means we are getting closer to possessions! Nothing is final until official possession letters are recieved; as a homeowner, please make sure we have your correct information on file so we can contact you! We’ll continue to post photos and updates on our Facebook page, so keep checking for the latest details on your new home.

Melissa @TheBlock