Buffalo at Silverado: April Construction Update

Construction continues to move along at a impressive pace in Buffalo at Silverado. Our crews are doing such a great job, we figured you’d want to see for yourself!

We’re blown away at the progress! Each day there is something new and exciting to tell you about. This month we’ve started to see the roofs going onto a few buildings, while framing continues throughout the site. Rough-in’s are also scheduled to start soon.

Here is a building-by-building update, along with estimated possession dates:

Building 1: Second floor is framed and trusses will be going up for the roof. August – September possessions.

Building 2: Foundations are in and we’re proceeding with the footings, then  framing will start shortly. Tentatively looking at October – November possessions.

Building 3: Excavating, cribbing process, basements and foundations are in the works and we’re tentatively looking at October – November possessions.

Building 5: Trusses are complete, the pressed board roof is being installed and shingles and rough-ins will be next. We estimate August- September possessions.

Building 7: Walls are going up, followed by the trusses and then the roof. Tentatively looking at October- November possessions.

Building 9: The roof is going on and shingles will follow.  Tentatively looking at August- September possessions.

Building 10: Framing is finished, the trusses are complete and the roof is going on. Tentatively looking at August- September possessions.

Building 11: Excavations have started,with cribbing and foundations set to follow.

Building 12:  Excavations are complete. Foundations have started and framing will start shortly. Tentatively looking at October- November possessions.

Come by for a visit, we’d love for you to see the changes in person.

Until next time,

Whitney@Buffalo