Canoe at Auburn Bay: October 2015 Construction Update

Here’s a quick update on construction this month in Canoe at Auburn Bay!

East Wing

  • Electrical and plumbing rough ins are completed and down to deficiencies with electrical working on common areas.
  • Elevator is 80% complete.
  • Gypcrete has been poured in units on 4th, 3rd and 2nd floors.
  • Siding is being installed into the last half of courtyard with paper starting on north side of building.

West Wing

  • Roof is being sheeted with shingles starting within the next few weeks.
  • Plumbers have started drilling and inserting rough ins.
  • Decks are in progress.

Parkade

  • Most of the block work is completed in the parkade. Trades are setting up the equipment for the power and HVAC systems.

 