Canoe at Auburn Bay: Construction Update for January 2015

Now that the holidays are over and everyone is getting back into their normal routines, it’s time to do Canoe at Auburn Bay’s first official construction update! This warm winter weather has been a real help since groundbreaking and our construction team is full speed ahead.

On the east side of the building we have about 80% of the exterior walls formed and will be pouring them, the stairwell and elevator walls early this week.  This week with that pour we will also be doing approximately 60% of the columns.

For the west side of the building we just finished shoring on our north and west banks and are currently digging down to bottom of footings so that we can start putting forms up for the footings next week. Shoring is the supporting of a building or structure with props to support the weight of freshly poured concrete.  Then we will follow with the walls and our transition to connect the east and west parkade in the following weeks.

Big news on the sales side of things! We’re launching the west side of this amazing development in early February. For all you Avi Urban homeowners, if you have a friend or know someone that may have missed out on a home in our first release, this is your chance to help pick your neighbors and their chance to own in this beautiful one of a kind apartment development. We love your referrals and hey who doesn’t love to get $1000!? 🙂   If you’re in the market, or know someone who is, please stop by and visit us at the presentation center to see the floorplans and reserve your spot for our upcoming release.

Stay tuned for more updates as we continue moving forward with construction!