Canoe at Auburn Bay: Construction Update March 2015

As this beautiful weather continues and we are getting closer and closer to the official start of Spring, construction is moving along onsite at Canoe at Auburn Bay!

For the East side of the building, we poured another section of the upper slab on Wednesday.  We have also poured some of the east retaining wall and the stairs into the parkade. For the West side of the building we are forming the first section of the upper parkade and getting ready to start pouring the top slab in the next few weeks.

As we move forward in construction stay tuned for more photos and updates! Also, if you haven’t been down to see us at the Sales Centre, stop by to see the plans and the finishing’s we offer in this amazing new condo development in Auburn Bay.

 

Kassy @Canoe