Construction update: Sawyer, Silverado

With two of our buildings in Sawyer, Silverado fully occupied and many happy homeowners settling into their first Christmas in their new home, we are delighted to give you the latest construction update for the final building in this award winning development.

Building 2000

Christmas is nearly upon us but there is no slowdown from the Avi Urban construction team as they make fantastic progress in the final building.

Siding of the building will be completed this Friday, December 19.

Work on the retaining wall on the north west corner of the building started this week.

Boarding and taping has been completed in all units.

Textures in the last seven units on the third floor will be completed next week before the Christmas break.

Cabinets will be completed in all units by Friday, December 19.

Hardwood, carpet & tile have been completed on the first floor as has granite.

Plumbing and electrical finals are to be completed on the first floor by Friday, December 19.

So, exciting times in Sawyer, Silverado! From all the team in Sawyer, we would like to wish you and yours a very Merry Christmas and Happy New Year!