Edison At Walden: Construction Update April 2015

It’s a gorgeous day out here in Edison At Walden. Sun is shining and it feels like summer is fast approaching, but what is also fast approaching is the completion of this awesome development. With only a few buildings left to take possession it’s hard to believe it was only a year ago home owners started moving in!

Building 5 &10- Congratulations to you home owners who have moved in. Hopefully you are settling in nicely and it’s starting to feel like home.

Building 4- Possessions are set for this month. So walk throughs and touch ups are happening now. Good luck to those of you moving in this month!

Building 9- Finishing touches are ongoing. Walk throughs and possessions are set for May.

Building 8- These homes have been dry walled and painted with kitchens installed, next is flooring. Siding is also now pretty much complete on this building.

Building 3- Homes are insulated with dry wall and taping starting. The exterior siding has also begun on this building, this is the last one to be complete!

Landscaping is ongoing but is set to be completely finished by July. Just in time for the summer! The front entry feature is to be finished by the end of this month, stay tuned for the finished product! This is also where mailboxes will eventually be located.