It was a gorgeous day out here in Walden, leaves blowing, sun shining and blue skies. I love fall. With such a beautiful October construction has been coming along. Took a walk around the site today to see what’s going on.

 

Building 1 & 2- Third floor is being joisted with the third floor walls going up.

Building 6 & 7- Framing of garage walls is completed.

Building 19 & 4- Garage pads are being poured.

Building 20 & 12- Are being back filled.

 

Foundation walls of building 4 are being poured, which means all building foundations are complete by next week! Once that’s finished and all buildings are back filled, framing will continue on each building over the winter.

Just a friendly reminder that Edison is a construction site and any visits to the site should be accompanied by Todd, myself or construction staff. Safety first!