Edison At Walden: Construction Update August 2014

Hot summer days means progress out here in Edison! Walking around site today it’s great to see how these new Calgary Townhomes are shaping up. Here is this months update for the progress on each building:

Building 16- Home owners have taken possession and are now moved in. Congrats to all of you on your new home!

Building 17 & 18 -These homes are in the final stage of touch ups with home owner walk throughs happening and possessions the end of this month! Hope you are all getting excited!

Building 15- Drywall is complete. Now heading into the finishing stages meaning cabinets, doors, and trim are being installed with flooring and painting following. Exterior siding is completed and driveways are prepped and being poured.

Building 19- The insulation is complete and dry walling has begun. Exterior siding is almost completed on this building.

Building 14 & 20- All inspections complete ready to start insulating and spray foam. Exterior siding has started on these buildings.

Building 13- Rough ins almost complete. Inspections expected next week.

Building 12 & 11- At rough in stage. Plumbing and HVAC complete, electrical on going.

Building 5- Back framing on the interior is complete. Starting rough ins on these units.

Building 10- Plumbing and HVAC rough ins on going.

Building 9 & 8- Back framing on the interior. Roof is framed, sheeted and being shingled.

Building 4- All floors framed. Trusses going up and sheeting the roof.

Building 3- Second floor joists complete, now framing third floor walls.

With all buildings now in action you can get a sense of what the community Edison will become. Come by the show homes to visit Todd and myself, with limited inventory you won’t want to miss out on this awesome development!

Melissa @Edison