Jackson at Walden: August Construction Update

Once again, we’re blown away with the progress in Jackson at Walden. Here’s a quick update on all the advancements we’ve been making :

Building 8, 9, 10, 11, 12, 16, 17 and 18 – Completed and all homeowners have taken possession

Building 15 – Painting and cabinets have started

Building 1 – Possessions are set for August and September

Building 7 – Texture and taping has started

Building 6 – Insulation has started

Building 2 – Possessions are set for September and October

Building 14 – Framing has started

Building 3, 4, 5, 13,  – Foundations have started

Around the site – Landscaping has been installed including planters along the front of Building 15.  The second garbage enclosure is almost ready for exterior siding.

Until next month!

Mikendra @ Jackson