Jackson at Walden: December construction update

This is the last construction update for 2016!! Can you believe the year is almost done? And in a deep freeze no less…but hopefully this arctic chill is gone before Christmas. Luckily for construction, we have had amazing weather this fall, meaning we were able to get a lot of work done at the Jackson at Walden site!

Here are the construction stages for each building: (in order of approximate possession date)

Building 10 – Insulation is complete and the drywall installation has begun

Building 9 – Rough-ins are well underway

Building 8 – Rough-ins have started

Building 16 – Framing is complete and windows are almost all installed

Building 17 – Framing is almost complete and windows have started going in

Building 12 – Framing is going well, the exteriors and stairs are framed and complete, and interior framing has started

Building 18 – Framing has started; currently the construction team is working on the second floor

Building 11 – Foundations are complete and framing will start soon on the garage

Buildings 1, 2, 6, 7, 15 – Foundations are poured and back-filled, we’re just waiting for our framers to be able to start

Buildings 3, 4, 5, 13 & 14 – Foundations will start in the spring

Around the Site – The garbage enclosure foundation is complete

Until next month,

TaraLynn @ Jackson