As we approach the end of August we are approaching the end of framing in Building 1!

Things are looking great out at the Sawyer site in Silverado, construction is moving along just as planned and we have two buildings underway and soon to be three. Check out our construction glossary for detailed information on the construction terms below.

Building 1 – The third floor is being leveled and trusses will be going up in a few days. Staircases are all going in this week. The roof will be sheethed and shingled in early September. Rough-ins have started, plumbers are on the first floor and electricians to follow next week. The balconies are going on this week with the first floor done already. By end of this weekend we expect to have all the balconies done for the entire building!

Building 3 –  All ofthe foundation walls have been poured except the south wall, that is to be poured Saturday. The undergrounds are being done and slab on grade to be poured by the end of next week or the following Monday.

Building 2 was released just over a week ago and we are over 20% sold! We’ll have more news to follow as we break ground! Make sure you register to keep posted on any exciting new updates on the new Calgary condos at Sawyer Silverado and community of Silverado.

We still have several great locations and floor plans available so stop by the Presentation Center and showhome to find out more information.

Nik and I look forward to seeing you!

 