Well Spring weather is finally here, and now we are getting excited to start preparing our homeowners in Building 1 for moving into their new home at Sawyer in Silverado! Construction on all three Buildings is moving along and the site looks amazing. Here’s a building by building update.

Building 1:

–        Flooring complete on the first floor and it looks great!

–        Lighting started this week on the first floor

–        Plumbing fixtures are being installed this week on the first floor

–        Painting has started this week on the second floor

–        Cabinets & counter tops are being installed this week on the third floor

–        Doors and trim are being installed this week on the third floor

–        Stone work on the exterior has started and we just love the way it’s looking!

–        Site grading started this week

Building 3:

–        Roof is complete

–        Electrical rough-ins have been completed this week

–        Drywall started this week on the first floor.

–        Siding started this week

–        Parkade ramp between building 2 and 3 is complete

Building 2:

–        3rd floor joists starts next week

–        Back filling & weeping tile have started this week

 

Stay tuned for more exciting updates for Building 1 and as Building 2 and 3 progress, photos and updates will be posted often to keep you informed of our progress!

 