Sawyer Silverado: November Construction Update

As we approach the beginning of the Calgary’s winter months and had our first taste of winter last weekend and more snow on it’s way! We’re seeing no sign of slowing down here at Sawyer inside the Presentation Center and especially onsite! Site grading will begin next week and we have already started construction on the street lights for the area. The development is really starting to take shape and is looking great.

Here’s an update for each building:

Building #1 – We now have the roof completely shingled! This is exciting because now we are able to start drywall. Drywall and insulation has started on the first floor of building 1000. Rough ins are nearing completion on all floors. We are still looking at a spring 2014 possession for these units and things are moving along nicely!

Building #2 – Well in our last update we were just pouring the footings in building 2000 and finishing the slab on grade. Now they have that poured we are starting on the foundation walls! This is exciting; once we have the walls of the foundation complete we are able to start the rough ins for the parkade.

Building#3 – All the parkade rough ins are complete in building 3000 and we are just preparing to pour the main floor slab. This will be another big milestone in the Sawyer development as next steps will be to start framing!

We are selling our final building at Sawyer and even though we are 60% sold, we still have many great locations and plans available. So, if you’re thinking about buying your first place or just want the no maintenance lifestyle of a condo come and visit Nik and I at our presentation center this weekend!

 