Sawyer Silverado: October 2013 Construction Update

Well it’s time again for another update on what’s going on at Sawyer with construction! Things are looking great on site with all three buildings well on their way. Here’s a building by building update:

Building #1000

The roof is up and the framing is complete. Windows and doors are almost all installed. The mechanical systems are being installed; boiler, hot water heater, HVAC and the city water will be connected and functional.

Rough-ins are being completed on the 3rd floor, with electrical working on finishing the 2nd floor. We have the roofers here all weekend putting the shingles on building 1.

 Building #2000

The excavation is complete for building 2 and the footings will be going in.

Building #3000

Underground parkade floor has been poured and the suspended slab (main floor slab) is being formed.

After having another busy week in the sales office we are now 50% sold in our third and final release at Sawyer. We still have many great locations left to choose from, so don’t wait any longer and come down to see us at our show suite and presentation center!

See you soon!

Kassandra and Nik @Sawyer Silverado