Wow!  There’s not a day that goes by where you can’t see the progress on the Sawyer Site!

Building #1 – Framing is coming to an end, the 3rd floor is nearly complete with the trusses nearing completion and the sheeting has already started. The 1st and 2nd floors have the plumbers moving right along with rough-ins and electricians are following right behind. Windows have been delivered on site and are being installed this week.

Building #3 – The gravel is going in now, which is the base for the slab on grade for the floor of the parkade. Next step will be to pour the concrete floor of the parkade! This is a big deal out here and is scheduled for next week.

Building #2 – Just weeks after our release of the last building in Sawyer, we are pushing 35% sold. With such a great start to our release we will be able to start the excavation of this building tomorrow. This means all 3 of our buildings will be under construction!

We’re very excited to see what the fall brings and watch all 3 of our amazing buildings in this development come up from the ground!

For those of your still on the fence about taking those first steps into homeownership or looking at maybe a change in lifestyle to the no maintenance condo living don’t wait any longer. Come down to the presentation center where Nik and I can show you the great options we still have available at Sawyer in Silverado!