Willow at Sherwood: Construction Update Jan 2016

It’s the first construction update for Willow at Sherwood for 2016! There has been lots progress and even more homeowners are moving in and calling Willow at Sherwood home.

Here is were each building is at now;

Building 3, 4, 5, 6, 7, 8, & 10 – All Completed, but there are a few left available for sale in building 8 and 10 if you are needing a quick possession!

Building 9 – The rough-ins are complete and the exterior work is about 95% completed as well, and we are getting close to starting insulation.

Building 1 – Rough-ins are complete and the exterior work is now well underway.

Building 2 – Rough-ins are finishing up, should be completed by the end of this week. The exterior work is going strong with wrapping the buildings with Tyvek (provides a water barrier between the outer cladding of a structure and the frame, insulation, etc., allowing water vapor to pass yet restricting air and liquid water infiltration), and now siding is just started.

Around the site – Not much is able to happen in winter, once spring comes around though we’ll be going full force with landscaping again

That’s all time next month! Until Next Time.