Willow at Sherwood: Construction Update March 2016

It’s officially spring and construction is moving into the final stages for the last three buildings in Willow at Sherwood.

It would be nice if we could start on landscaping again, but you just never know what Calgary weather could bring, so it will still be a few months before that gets moving again. With that said, all the building exterior work (siding, brick and decorative details) will be finished soon!

Here is the break down by individual building:

Buildings 3, 4, 5, 6, 7, 8 & 10 – All completed, only three quick possessions left that you could move into right away!

Building 9 – Insulation is complete and it’s looking like dry walling is almost complete as well. The doors and baseboards have started to arrive.

Building 1 – Rough-in’s are complete, insulation will be starting soon. As for the exterior, siding is finishing up and then the brick work will begin.

Building 2 – Rough-in’s are complete, insulations will be able to begin soon. The exterior siding is almost done and then brick work can begin.

That’s all for this month, until next time.

TaraLynn @ Willow at Sherwood