Willow at Sherwood: Construction Update Nov 2015

It’s getting close to the end of the year and the Christmas holiday is now upon us. Hopefully you’re almost done with your Christmas shopping because the malls are busy! Luckily the weather hasn’t been that bad! Which is also great news for Willow at Sherwood construction and the homeowners that are moving in!

Over 50% of the construction in Willow at Sherwood is now complete and many lucky homeowners are preparing to spend the first holiday season in their new home!

Here is where construction is at now:

Building 3, 4, 5, 6, 7, & 8 – Complete and homeowners have moved in

Building 10 – In the final stages of finishing. The tile work and carpet has finished and hardwood has started to go in. Exterior work is complete

Building 9 – Finishing rough-ins. Exterior work is well underway, siding is going to finish up this week and the brick work is about 50% complete

Building 1 – Rough-ins are well underway with electrical work finishing up. Exterior work will be next

Building 2 – Rough-ins have started with plumbing

Around the site – The remaining landscaping will be on hold until Spring 2016. The garbage enclosure is complete and the mailboxes are in their temporary locations until the permanent ones are available.

Until next time!

TaraLynn @ Willow at Sherwood