Winter is coming…OK maybe not as dramatic as Game of Thrones, but you can feel the chill in the air. At least it’s not here yet and because it’s not here yet we can still move forward on landscaping! You heard me landscaping is starting at Willow in Sherwood, we owe it to the El Nino’ weather going on that we haven’t seen snow yet and can still plant this late in the year.

Here is Willow’s Building by Building progress;

Building 3, 4, 5, & 6 – All complete and home owners moved/moving in and excited to see our Landscapers on site

Building 7 – Final tile work and finishing touches are happening, and brick work is finishing up

Building 8 – Cabinets are in, now finishing can happen with Flooring, countertops and tiling and the brick works is finishing up.

Building 10 – Drywall is complete, we are ready for Cabinets to go in. The exterior siding is finishing up and the brick work has started.

Building 9 – Rough-in’s are finishing up, windows are in and we’re getting ready  for siding to start

Building 2 – Rough-ins are underway, the driveways were poured

Building 1 – Rough-ins are getting ready to start

Around the Site – The Garbage enclosure has finished being framed, landscapers are set up most of the underground sprinkler system around Willow and working on the soil/grading in the courtyard. Landscapers have even started planting with trees going in the courtyard!