Willow in Sherwood: Construction update Feb 2015

It’s is exciting to see all the work that has happened on site over the past month. This mild winter weather might be bad for the ski hills, but it sure makes for great conditions on site for construction. By looking at the pictures you can tell I took them on two different days from the looks of the snow on the ground (or lack there of)! Four buildings have now seen construction start, with others starting soon!

Here is a look at where construction is at now;

Building 3 – The foundations are completed and framing has started, the garage level is complete and work has begun with the 2nd floor

Building 4 – The Foundation walls have been completed, framing is going to begin soon

Building 5 – The forms for the footings are almost completed, the concrete will be poured next, and then the forms for the foundation walls will be set up

Building 6 – The foundations have been dug and the forms for the footings will be set up soon.

Building 7, 10, 9, 8, 2 & 1 – work will being soon

Around the site – Lamp posts are in around site and we’re hoping to get started on the recycling/waste enclosure soon.

I’m excited to see where next month construction update and photo’s will be at!

Until next time.

TaraLynn @ Willow in Sherwood