Willow in Sherwood: Construction Update Jan 2015

This is the first construction update of the new year and it’s off to a great start! Work on the first two buildings in Willow at Sherwood is now underway! This is always the exciting time, now that work on the townhomes has begun you will see something new happening every month

How I normally format construction updates is to break it down by each individual building in Willow and where that building is at in the construction phase. I also update as site progresses, so where Roads, Landscaping and the Waste/Recycling building are at in completion.

Here is the break down of where each building is at in construction;

Building 3 – foundations were poured last week and when I was on site Thursday the forms were coming down so you can see the foundation walls.

Building 4 – The footings were poured last week and the forms for your foundation walls are going to be set up right away

Buildings 1, 2, 5, 6, 7, 8, 9 & 10 – All other Buildings will have work starting soon. Work begins in the order of possession timeframe.

Around the site – The road ways and curbs are already in. Landscaping is seasonal so nothing will happen there until summer. The Waste/recycling enclosure will begin soon so watch this space.

Until next time 🙂