August at University District: Construction Update

It has been extremely busy on site and our construction crew has been working around the clock getting the foundation poured and supports in for the parkade.

As of today we have over half of the columns poured for P2 along with the start of the elevator shaft and start of the stairwell on August’s side of the building. Last week they completed the raft slab pour.

All of the columns and interior walls have been poured on the hotel side. Crews have been working on weather proofing for exterior walls and hopefully will start pouring these this week. We are aiming right now to have 2/3 of the slab poured for P2 at the end of this month.. Anchors have been finished and are in the process of being tested.  Crews have continued to bulk out dirt and back fill around column pads.

Bre @ August