August is up, up and away! Since the last update the second level slab has been poured. The framers have been standing the walls and are currently joisting level 3. The plumbers are running pipe on P1, P2 and the CRU levels, plus electrical is pulling wires through. The parkade is being painted which will be done in sections as the shoring posts get pulled out. HVAC is starting to go into the parkade as well.

In other news the Central Park groundbreak happened last Friday and is projected to be complete for 2021!