Edison At Walden: Construction Update November 2013

Construction is progressing out here in Walden, at your New Calgary Townhome. Walking around the site today framing crews were busy at work. With four buildings now well into framing stages, the roof lines and unique architecture of these townhomes is a show stopper! This community is taking shape and you won’t want to miss out!

Building 1- Windows are being installed. Interior framing being finished meaning stairs, stub walls etc

Building 2- Third floor is finshed with the roof now being constructed.

Building 6- Third floor walls are being framed.

Building 7- Joisting the third floor walls in preparation for the roof.

Building 16- Framing the mechanical floor. Preparing for the garage to be framed.

Buidling 17- Garage is finished framing.

Next week primary services like Enmax, Atco are being installed.

Home owners just a reminder of the event this upcoming Tuesday November 19th. Please RSVP if you would like to attend and meet your new neighbors!

Melissa @Edison