Edison At Walden: Construction Update November 2014

Construction continues to move along here with these new Calgary town homes. The bitter cold hasn’t kept our trades from working hard! Here is the latest update:

Building 14 &20-Walk-throughs and touch ups happening. Exciting for those in these buildings getting possession in the next few weeks.  Good luck with the move hopefully the weather co-operates!

Building 13– These homes have finished dry walling with taping and painting now happening.

Building 12– Spray foam and insulation are done with drywall beginning. Exterior siding completed on this building.

Building 11– City inspections are complete. Spray foam and insulation are being started on these homes. Exterior siding complete.

Building 5– Back framing is complete with frame check to follow.

Building 10– Rough ins are complete. Back framing the interior. Exterior siding is near complete.

Building 4– Electrical rough ins now starting.

Building 9– Electrical rough ins complete.

Building 8– Rough ins for HVAC, plumbing and electrical now starting.

Building 3– Framing is now complete, ready to start rough ins.

We’ve had some enquiries about what’s happening next to our show home. This is going to be the Edison entry feature and will also be the permanent spot for mailboxes. Stay tuned for the outcome on this development!

Melissa @Edison