Jackson at Walden: October Construction Update

It’s officially Fall and we’re thrilled to report we’ve had lots of great progress here at #JacksonAtWalden. We had to pause construction while the curbs and paving were underway, but now that it’s complete we are going full force with construction again. And things are moving fast!

Here is the breakdown for where each building is in construction process:

Buildings 1, 2, 3, 4, 5, 6, 7, 13, 14, 15 – Will be underway soon!

Building 8 – The garages are having the concrete floor poured.

Building 9 – Shingles have arrived so work on the roof is getting ready to go.

Building 10 – The rough-ins (electrical, plumbing, etc.) are almost complete. We’re getting ready to start siding.

Building 11 – Next up to have the foundations dug.

Building 12 – The foundations are dug and we’re getting ready to have the footing concrete poured.

Building 16 – Framing is well underway with the second floor going up.

Building 17 – Framing has started with the ground floor (the garage level) and the driveway concrete was just poured.

Building 18 – The foundation has been dug and we’re ready to run the main utility connections to each unit.

Around the Site –  The preliminary curbs and roads are now complete.

That’s all for this month.

Until next time,

TaraLynn @ Jackson at Walden