Jackson at Walden: September Construction Update

Hi Everyone;

We have some great photos and building updates to share with all of our buyers!

Jackson at Walden is coming along and we are so excited to fill you in.

Building 8 & 9- Both buildings are finishing framing at roof level,  and rough-in’s will begin in a couple weeks.

Building 10- Windows are in, and each patio has been poured. The siding is next and is on schedule.

Building 16 & 17 – Garage floors have been poured, main floor framing has started and we will be moving to the second floor in a few weeks.

The curbs are complete on the interior roads, and we’re waiting on asphalt. Road completion is on target. Aiming for the end of the month for completion.

Stay up-to-date on your building with our monthly construction updates!

Until next time,

Whitney @ Jackson