The Post in Nolan Hill; Construction Update June 2014

Have you had a chance to drive by the Post in Nolan Hill? If not, I would take a drive and see the progress that has been happening and will be happening in the next few weeks. But don’t worry if you won’t be able to make it, photos will be posted in the Facebook photo album!

Here is a quick summary of where each building is at this month:

Building 1 – Roof is almost complete, windows with be delivered soon, and rough-in’s (water, electrical, sewer) look like they will be able to start later this month.

Building 3 – 3rd floor is finished being framed and the roof has started to go up.

Building 2 – Underground plumbing is being completed and framing is scheduled to start later this week/ beginning of next week.

Building 4 – There is digging happening around the foundations, we will soon be able to being digging your foundation.

Building 5, 6 & 7 – Waiting for foundations to be dug.

Around the site – The Nolan Hill green space just north of The Post is starting to take shape with landscaping underway.

Keep it locked to our Facebook page for more photos as construction continues this summer!