Prospect Rise Kincora: Construction Update Feb 15

Construction at Prospect Rise Kincora is almost 50% Complete. We’ve had 5 of our 10 buildings turned over to our homeowners with 2 more buildings set to have homeowners move in by the end of March.

Building 5, 6, 8, 9 & 10 – All completed, new home owners have moved in and making it home

Building 7 – Possessions by homeowners are starting to happening over the next couple weeks

Building 1 – Possession Letter have been sent out. The finsihings stage is underway, this means your cabinets and countertops have started going in and flooring is the last element to go in before we start touch-ups!

Building 2 – Drywalling is complete walls have been sanded and had the first coat of primer. Trim and doors will start going up next.

Building 3 – Framing and the roof are complete. Rough-ins are also complete, insulation is about to start.

Building 4 – Rough-ins are complete, insulation has started and drywall will be able to start soon after. Siding has started going up.

Around the Site – The Garbage enclosure framing is complete, next you will see the roof going on. Decks are going up around the site. By Spring we will be able to Landscape too!