Prospect Rise Kincora: Construction Update Nov 2013
There has been some excellent progress on the Prospect Rise Kincora Site, with 4 of the 10 buildings having homeowners move in by the end of November!
Here is the break down of where construction is at in each of the buildings;
Buildings 6, 9 & 10 – All three buildings are ready for homeowners to move in by the end of this month. Finishings/touch-ups are either completed or very close to being done!
Building 8 – Flooring installation has started, touch-ups will start in the next week in order to be ready for homeowners to move in at the end of the month.
Building 5 – Drywall is being completed
Building 7 – Rough-in are complete and being inspected, soon insulation and drywall will be underway.
Building 1 – Rough-ins are well under way, the garages are being prepped for concrete to be poured.
Building 2 – Windows are in and rough-ins have started
Building 3 – The 3rd floor and roof are being framed
Building 4 – The 3rd floor and roof are being framed
Around the Site – The Garbage enclosure is being constructed and more driveways, sidewalks and curbs were poured before the latest snow fell.
TaraLynn @ Prospect Rise Kincora