Savanna Urban Terraces: Construction Update

It’s a new year and, up to this point, the weather has been very kind to our construction team, allowing them to get a lot of work done!

Here’s a building-by-building progress update of the Savanna Urban Terraces:

Building 1: This building is complete and all the happy homeowners have moved in. And if you’re looking for an investment, ask us about the show homes, which are available for our exclusive lease back opportunities!

Buildings 2 & 3: Both are complete and our homeowners have all settled in.

Building 4: Exterior work is finishing up and siding almost complete. Inside the homes, the drywall is done and will mud and prime the walls next, getting them ready for cabinets!

Building 5: Drywall and mudding is complete, and the cabinets and countertops have been installed. Now we get to start the finishings, which include interior doors, baseboards, lighting and flooring — just to name a few.

Building 6: Foundations are dug and the concrete foundation walls are complete.

Building 7 & 8: We will begin digging the foundations in a couple weeks, so stay tuned for the next update or stop by the sales centre to check it out!

Until next time,

TaraLynn @ Savanna