Savanna Urban Terraces : July Construction Update

Change is a good thing — especially when it comes to construction progress!

A lot has changed in Savanna Urban Terraces since our last construction update! The framing on all the buildings in our first phase (buildings one, two and three) are near completion and we’re getting close to starting construction on phase two!

And because we know you’re just as excited as we are, here is a building-by-building update:

Building 1 – Framing and the roof is completed, windows are in and rough-ins (the heating, plumbing, and electrical) are almost done. We’re especially excited for the completion of this building since it will be the location of our new showhomes, which we expect to open early in the fall!.

Building 2 – Framing is nearly complete and our team is about to begin on shingling the roof and installing windows.

Building 3 – The roof framing began last week and should be completed this week, followed by the roof shingles going on.

Buildings 4 & 5 – These buildings are in phase two, which we’re close to starting construction on. Once our construction team gets the green light, they’ll start digging the foundations.

Buildings 6, 7, & 8 – As part of the third (and final) phase, these buildings will be released for sale shortly.

Until next month,

TaraLynn @ Savanna