Sawyer Silverado Construction Update: July 2013

It’s been one busy July in Sawyer Silverado! Our team has been working hard and there is tons of activity on site as we work to frame and put in roads. Here’s what’s going on in the new Calgary condos at Sawyer Silverado:

We are currently 50% framed on the second floor for Building One and only a three remaining homes! Take advantage of the spring 2014 possession with the remaining south facing Corner A plan.

We are anticipating completion of the framing in Building One for September 2013. Next stage will be rough-ins, which will begin the first couple weeks of August. We will be starting with plumbing of the building, then all the electrical and mechanical rough-ins for the units and common areas. This is an exciting time in the construction because you are able to see the progress.

Excavation started just over a week ago in Building Three and now we are preparing the support pads and footings for the foundation. Once the slab on grade is poured the wiring for the parkade will being and shortly thereafter a building starts to rise from the ground!

Stay tuned for some exciting new on the release of Building Two. Building Two is our final release in the Sawyer Silverado development. You definitely do not want to miss out on your opportunity to own in this beautiful SW Calgary community.