The Enclave: Construction Update – October 2013

Our team has made major progress this fall, and we’re excited to see how these new Calgary townhomes are coming along! With so many more people already moved in, the development is almost complete.

We recently caught up with site superintendent Terry to get the details on how The Enclave is going, and what his team is currently working on. Here’s where we’re at:

Landscaping is nearly complete! The courtyard looks amazing and homeowners are already utilizing this great amenity. The team will be finishing up the roads this week and next, along with the street lights and other exterior lighting.

Building 10: Homeowners have just moved in!

Building 17: Homeowners have just moved in!

Building 18: Homeowners are moving in this month. We’re currently taping the drywall and priming, with final cleaning and walk-throughs to happen later in October before possessions take place.

Building 20: Homeowners are moving in this month. The team is taping the drywall and paint will come soon after.

Building 9: Homeowners will be taking possession in November. Right now the team is working on drywall, followed by taping and painting. It’s cool to see the final few buildings come together!

Building 1: Homeowners are moving in come November. We’re finishing up rough-in’s (the stuff inside the walls that makes your home run) and completing inspections. Once that’s done, we’ll move on to drywalling.

As new homeowners start to move in, we’d love to see how you’ve made the space your own and how you’ve decorated. Post photos of your new place on our Facebook page and share how you’ve made The Enclave your home.

Kassandra @ The Enclave