The Enclave February Construction Update

For all of our homeowners waiting to hear what’s happening at The Enclave in Castle Keep, here’s an update on the progress of each building.

Building #1 – Ready to frame, the footings have been done and foundation is completed. We will see the building start to come up from the ground now.  

Building #6 – Building 6 is getting close to being finished! We are at the textures stage, which is when the ceilings are being done with knockdown, flat paint or stipple.

 Building #7 – We are in the process of having all our proud homeowners move in!

 Building #8 – The finishing touches are being put on our units in building 8 and we will be having another building moved in shortly!

Building #9 – Backfilling is when they replace the excavated soil after the wall foundations (footings) have been completed, so they can pour the main (garage floor).

Building #10 – Ready to frame.

Building #11 – We are at the drywall stage; we just finished rough-ins and next will be paint and flooring!

Building #13 – Ready for inspections and we will be ready to move in early spring!

Building #14 – Rough-ins are being done on building 14, rough-ins are when all the wiring, electrical and plumbing is installed in the walls, next will be dry wall.

Building #15 – Rough-ins are being done on building 15, rough-ins are when all the wiring, electrical and plumbing is installed in the walls, next will be dry wall.

Building #16 – Ready to frame.

Building #17 – Foundation walls

Building #18 – Footings (the concrete wall foundations) are complete, next stage would be framing!

Building #19 – We are finishing up the framing and then the roof will be up.

Building #20 – Footings

Building #21 – Framing first floor has started for this beautiful location overlooking the pond.

If you have any other questions regarding timelines or the status of your building outside of the construction updates, please contact your customer service representative Tara Lyseng at tlyseng@homesbyavi.com.