The Enclave: October Construction Update

Our team at The Enclave has been hard at work this fall building new Calgary townhomes. The development is now sold out, but we know there are plenty of eager homeowners waiting to move in!

Take a look at the progress of each building to see what stage your new home is at:

  • Building 1: Ready for backfilling (garage floors)
  • Building 3: Exterior done, front landscaping, interiors completed with some touchups, driveways hopefully next week
  • Building 4: Exterior complete, landscaping next week, tile and carpets (turnover in end of Nov), all driveways in
  • Building 5: Taping the walls, turnover at end of November, exterior is complete, driveways coming in,
  • Building 6: Framing still being done
  • Building 7: Working on exterior, framing confirmed, insulating in the next couple of weeks
  • Building 8: Shingling and working on rough-ins
  • Building 10: Excavating, starting foundation next week
  • Building 11: Rough-ins and shingling in the next couple of weeks
  • Building 13: Now working on framing the roof
  • Building 14: Working on the 3rd floor subfloors, framing complete on 1st and 2nd floor, framing 3rd
  • Building 15: Ready for backfill, foundations are in
  • Building 19: Backfilled and ready for framing in the next 2-3 months
  • Building 21: Backfilled and ready for framing, ahead of schedule

Any questions about the progress of your new home? You can connect with your customer service representative, Tara Lyseng, at (403)536-7078 or tlyseng@homesbyavi.com