Willow in Sherwood: Construction Update Dec 2014

Although the appearance of the site for Willow in Sherwood isn’t showing major changes yet, there is still a lot happening on site and behind the scenes!

The roads have been poured, I know it’s hard to tell by just looking at the pictures, but you can see that the manholes are no longer jutting out of the ground and the roads are almost flush with the curbs. You can really see the difference when looking at last months construction update compared to todays though.

We’ve also been waiting on Enmax to visit the site, they are to come and set up the permanent power to the site. This makes it a lot easier for us and our trade workers as they won’t need to rely on generators to supply power to all those power tools used during construction!

Foundations will be starting in January with the first anticipated possession to occur in approx. August/September 2015. With that being the case I will have more to tell you in the January construction update!

I will end this final construction update for 2014 by wishing you and yours a Happy Holiday and a very Happy New Year

Until Next Year!

TaraLynn @ Willow in Sherwood